Sunday, April 24, 2011
04-23-2011: Hardwood floors, day 6
We didn't get a lot of flooring down Saturday. Rick finished out the hallway from the living room to the master bedroom while I finished grouting in the master shower.
We spent most of the afternoon in town running errands. We bought 3 toilets, pull-down stairs for the attic, 3 of 4 mirrors (the 4th is on a truck and will arrive Tuesday or Wednesday), a cat door into the utility closet ("para gatos grandes"--Minx didn't quite meet the weight limits on the regular size cat doors), grout sealer, etc.
Sunday, we'll work on hardwood floors in the master bedroom and closet, finish grouting around the master bathroom tub and floor areas, and put some kind of flooring down in the utility closet before the plumber arrives tomorrow and starts installing the water softener & reverse osmosis systems.
Subscribe to: