08-25-2010: Electrical

The electricians worked all day again.  The plumber said he would be here but didn't show up.  The HVAC guys are supposed to be here tomorrow.  The cedar beams and ceiling were delivered today, and the framers will be back tomorrow to finish up the front entrance stuff.  Most of the cedar beams can't be installed until the front and back porchs are poured, but they can't be poured until the brick is laid.  Rick is getting closer to having all of the caulking done but will have some more when the framers finish tomorrow.  The eaves should get painted fairly soon, and the roofers can then get the shingles on.  We are still waiting on windows and patio/front doors.   The last picture is the full moon rising at the end of the street.