10-08-2010: Taping/bedding/texture finished; brick delivered; cabinets continue










When I backed out of the driveway at 6:42am, the brick truck was sitting in the road in front of the house waiting for the gate to be opened.   It was over 1 hour and 15 minutes before sunrise!

The wall texture was finished by lunch.  We used an orange peel texture, and it looks like they did a great job. 

The brick layer will start either tomorrow or Monday depending on if the sand is delivered tomorrow.  The mortar was delivered this afternoon.

Rick spent all morning dealing with the brick and texture stuff, but continues his work on the cabinets.