Saturday, January 29, 2011

01-29-2011


Published with Blogger-droid v1.6.5

Thursday, January 27, 2011

Wednesday, January 26, 2011

Tuesday, January 25, 2011

01-25-2011: kitchen drawers



Published with Blogger-droid v1.6.5

Monday, January 24, 2011

01-24-2011


Rick is working on drawers, and I had a successful shopping trip tonight after work and picked up a bar refrigerator and stair treads.

Sunday, January 23, 2011

01-23-2011: Trim finished, drawers started





Rick has essentially finished all of the trim (except we're going to add more crown molding to an area in the basement) and began building drawers today.  The kitchen drawers have to be constructed a little differently than normal because we are using soft-closing drawer glides, but Rick figured them out today. 

When the kitchen drawers are finished, the doors and drawers will be hung in place and we'll hire the staining crew to stain and seal the kitchen, bar, living room beam, office/pantry doors, entertainment hutch area, and front door.  Rick will then get started with painting walls, windows, trim, and bathroom/utility room cabinets.

Saturday, January 22, 2011

Thursday, January 20, 2011

01-20-2011: Kitchen and bar doors & drawer fronts


Published with Blogger-droid v1.6.5

Sunday, January 16, 2011

01-16-2011: Looking back......(southwest corner of property looking to east)

01-15-2011
05-17-2010    

(note markers for house in background)
08-15-2009
07-26-2009
05-10-2009
09-27-2008

driveway being poured
08-08-2008
04-15-2007
01-21-2007
10-22-2006
09-03-2005
Aug 2005

01-16-2011: Looking back......(southwest corner of property looking to north)

 01-15-2011
 05-11-2010
 01-31-2010
08-15-2009
 07-26-2009
 12-14-2008
09-27-2008
 08-08-2008
 04-15-2007
 01-08-2006
08-2005

01-16-2011


This is a better shot of the ceiling beam in daylight.  We've ordered some crown molding for the sides.  Minx likes the new window sills. 

The cabinet doors and drawer fronts are being made by a local cabinet guy right now and should be ready this week.  Rick is finishing up the trim and will begin building drawers very soon.  He's gotten several bids on staining and sealing the kitchen/bar cabinets, living room beam, front door, and office/pantry doors, and we're hopefully not too far away from getting that started.  It should only take a few days.   He's also getting close to being ready to paint.

Thanks to some really nice weather today, Rick finally put up the beams on the back porch and moved the supports to the front in preparation for pouring the front porch sometime soon.

Saturday, January 15, 2011

01-15-2011






Thursday, January 13, 2011

01-12-2011


Published with Blogger-droid v1.6.5

Rick has been working on the living room beam and finishing up the trim.  Travis has been caulking and filling nail holes.  Rick started working on the stairs yesterday, so maybe there will be some interesting pictures to post.

Saturday, January 8, 2011

01-08-2011


Published with Blogger-droid v1.6.5

Randy moved some dirt piles around with the tractor and started working on the front porch area before the cold weather arrived.